CLUBHOUSE EXTERIOR UPDATE

Week of 11/28-12/5:  To date –  Dry rot removed from entire structure, insulation installed, plywood walls installed to reinforce structure and hold new siding, tar papered entire building, taped, wrapped and sealed all window frames, installed new hardy plank siding and trim on the entire building.

Thank you to Jim Groves:  New electrical wiring, refurbished our exterior lights for all entrances.

The new doors are starting to arrive and will be installed.

We are moving on to the pool entry arbor, completing trim on the front of the clubhouse, window sealing, new gutters, cabana/pool sidewalk repairs.

This will leave painting and sealing of the chimney as temperature allows.